Case Study - Alcatel-Lucent, Vimercate (MB)

Project data

  • Customer
  • Alcatel-Lucent
  • Value
  • €9.000.000
  • Area
  • 27.000 sq m
  • Programme duration
  • 37 weeks
  • Completion date
  • July 2014
  • Project Manager
  • Michelangelo de Lalla
  • Architect
  • DEGW
  • M&E Engineer
  • Lombardini 22
Alcatel

Overview

In 2013 ISG was awarded the fit out of new headquarters for leading global telecommunications company Alcatel-Lucent. The project was located inside the Energy Park in Vimercate – a well known industrial business zone on the outskirts of Milan.

The project

ISG carried out the refurbishment of five new buildings covering an area in excess of 35,000 sq m. The first building required work to the foyer and auditorium including the construction of a new boardroom and training areas. The second building comprised the installation of plant and a power centre on the roof, with offices and IT rooms installed over three floors as well as the construction of a product display room. The remaining buildings included the construction of offices, IT rooms and laboratories. The scientific laboratories all required extensive MEP works and are similar – in terms of system equipment - to the works we deliver in our data centre projects.

Alcatel